Juanita Beach Park’s bathhouse project held by Hearing Examiner

The city may decide to appeal the ruling to the Washington State Shorelines Hearings Board.

  • Monday, July 9, 2018 9:17am
  • Life

A June 29 decision by the city of Kirkland hearing examiner has delayed the project to replace the Juanita Beach Park bathhouse.

The city had applied for three variances as part of the Juanita Beach Park Bathhouse project. The variances would have allowed the bathhouse to be placed in the designated wetlands and buffers adjacent to Juanita Creek, which runs through Juanita Beach Park.

The variances would also preserve existing park space and beach access rather than requiring they be fenced off. In return for the variances, the city proposed significant restoration of Juanita Bay Park wetlands with a much higher ecological value.

The city is considering appealing the ruling to the Washington State Shorelines Hearings Board.

“This project provides so many solutions for our community and our natural environment, and we are determined to see them through.” said Lynn Zwaagstra, Kirkland’s Park and Community Services director, in a press release.

The variances were needed because the Shoreline Management Act prevents building construction in wetlands and their buffers unless the applicant can satisfy numerous criteria, such as demonstrating that no other suitable location for the building exists and that impacts are appropriately mitigated.

City staff chose the location of the bathhouse based on community feedback collected during the Juanita Beach Park master plan’s two-year process. The reasons for the community’s preference for the location included its open views, to maximize the lawn and play space and to provide a buffer between the natural forested area and the play area. The location was also chosen because it would improve lifeguards’ response times to emergencies by stationing them closer to the beach.

To compensate for the impacts to the wetland and buffer areas, the City’s project team members worked with staff from the Washington State Department of Ecology on a plan to enhance wetlands along Juanita Creek and at Juanita Bay Park by removing invasive species and planting native wetland species.

More information on the bathhouse project can be found on the project webpage online.

More in Life

City of Kirkland issues traffic alert, July 13-15, Marina Park

Kirkland Uncorked will last the weekend, traffic delays expected.

EvergreenHealth to Host Free Pelvic Health Seminars this July

Drs. Lora Plaskon and Mia Swartz will host the educational seminars on July 11, and July 26.

Kirkland City Council seeks volunteers for Public Safety sales tax proposition committees

Volunteer committees will make statements for and against proposed sales tax ballot.

Two teenagers injured when struck by vehicle in Kirkland

The accident occurred on July 5 on northbound Lake Washington Boulevard.

Juanita Beach Park’s bathhouse project held by Hearing Examiner

The city may decide to appeal the ruling to the Washington State Shorelines Hearings Board.

My Favorite Martins

Steve Martin and Martin Short discuss bringing their two-man comedy extravaganza back to Seattle.

State Supreme Court ruling highlights petition requirements

The deadline for initiative petitions to be submitted is 5 p.m. on July 6.

Local author connects women, mothers through humor

Heather LeRoss chronicles motherhood, womanhood and “wife-hood” in new book

Second annual Panther WellFest educates students on how to have healthy lifestyle

The event served to educate students how to eat healthy, manage stress and find fun in exercising.

Most Read